Map Project
A Molybdenum Autoclave Plant was a large brown field facility to upgrade molybdenum concentrate (molybdenum sulfide) into chemical and technical grade molybdenum using a proprietary autoclave process. The project started detailed engineering in early 2010 but then needed additional support. PSE was invited to supply needed support. PSE provided the Mechanical Manager for the project and many others. PSE was requested to remain to completion.
PSE RESPONSIBILITES AND WORK INCLUDES:
Scope, schedule, and budget for the detailed mechanical design effort
Specifications, bid review and vendor document reviews for 750 plus capital equipment items
Client design reviews
HAZOP Meetings
Construction assistance
Inter-disciplinary document reviews
General Arrangements, mechanical design drawings, interfacing and support of the structural,
On-site design/build support
Piping, and electrical disciplines